A landlord who receives a disrepair letter of claim on or after 30 November 2026 has 20 working days to object to the tenant's choice of surveyor. Miss that window and the tenant's nominee becomes the single joint expert, instructed on the tenant's own letter of instruction. That is one of the central mechanics of the revised Pre-Action Protocol for Housing Conditions Claims (England), approved by the Master of the Rolls on 30 October 2026 and in force from 30 November 2026 [1][2]. For anyone involved in single joint expert surveyor work on housing conditions claims in Kingston upon Thames and the surrounding boroughs, the new text is worth reading before the first letter arrives.
Key Takeaways
- The whole protocol has been replaced, with effect from 30 November 2026.
- The default model for expert evidence is a single joint expert, with a joint inspection by each side's expert as the fallback.
- Key deadlines are counted in working days: 20 for the landlord's response, 20 for the inspection, 10 for the report.
- Experts must be instructed with CPR Part 35, Practice Direction 35 and the 2014 guidance on instructing experts in mind.
- The specimen letter of instruction now asks the expert to say whether a hazard is a significant hazard or an emergency hazard under the Awaab's Law regulations.
What has changed and when
The Ministry of Justice summary says the revisions emphasise alternative dispute resolution, highlight urgent exceptions to the protocol, and take account of the Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025, the regulations that give effect to Awaab's Law [2].
The date is not a coincidence. The second phase of Awaab's Law also starts on 30 November 2026, extending the range of hazards that social landlords must investigate and fix within fixed periods. The protocol is the procedural partner to that change: it governs what happens when a tenant says the landlord has not done what the law requires.
Which claims the protocol covers
The protocol applies to civil claims by tenants and other occupiers about the condition of residential premises in England. Its scope includes claims under [1]:
- section 11 of the Landlord and Tenant Act 1985 (the repairing covenant for structure, exterior and installations);
- sections 9A and 10A of the same Act (fitness for human habitation and the Awaab's Law duties, the latter presently applying to social landlords only);
- section 4 of the Defective Premises Act 1972;
- nuisance, negligence and the terms of the tenancy.
Prosecutions under section 82 of the Environmental Protection Act 1990 are outside it.
How the single joint expert surveyor process works in housing conditions claims
Section 7 of the protocol sets out the route to expert evidence [1]. In outline:
| Step | What happens | Time limit |
|---|---|---|
| Letter of claim | Tenant names a proposed expert and encloses a letter of instruction | Start of the clock |
| Landlord's response | Landlord replies and may object to the expert or the instruction | Normally 20 working days from receipt |
| No objection | Tenant's expert is instructed as single joint expert on the tenant's letter | After the 20 working days |
| Objection | Each side's expert carries out a joint inspection | Agreed between the parties |
| Inspection | Property is inspected | Within 20 working days of the landlord's response |
| Report | Expert's report, or agreed schedule after a joint inspection | Within 10 working days of inspection |
Several further points matter in practice.
- Separate instructions are allowed. A landlord who accepts the expert but not the tenant's questions may send its own instructions to the single joint expert.
- Costs are shared. The cost of a single joint expert is split equally between the parties. Terms of appointment should be agreed at the start.
- Two experts are not guaranteed to be paid for. Where each side instructs its own expert, the court decides later whether both sets of fees are recoverable. Expert evidence is limited to what is reasonably required, and the court may cap fees.
- Early instruction is possible. A tenant may instruct an expert before the usual timetable where there is a significant risk to health and safety, where an interim injunction is needed, or to preserve evidence.
The protocol names two places to find an expert: the Chartered Institute of Environmental Health consultants directory and the RICS Find a Surveyor service [1].
What the expert's report must cover
The expert is asked to report on all the poor conditions at the property that the landlord ought reasonably to know about, and to provide:
- a schedule of works needed to put them right;
- an estimate of the cost of those works;
- a list of any works that are urgent.
The specimen letter of instruction in Annex B goes further. It asks the expert whether a hazard is a significant hazard or an emergency hazard within the 2025 Regulations, whether it is safe for the household to stay in the property, whether alternative accommodation is needed, and whether advice given to the tenant was adequate [1].
Those are not questions that can be answered from a quick walk-round with a damp meter. They call for a proper diagnosis of cause: readings taken and recorded, ventilation and heating assessed, construction and defects identified, and reasons given. A report that puts mould down to "lifestyle" without measurements will not survive this framework.
The expert's duties
The protocol requires the parties to have regard to CPR Part 35, Practice Direction 35 and the Guidance for the Instruction of Experts in Civil Claims 2014 [1]. In plain terms:
- the expert's duty is to the court, even at the pre-action stage and even when one side chose them;
- the report must set out the instructions received, the facts relied on and the reasoning;
- a single joint expert must deal even-handedly with both parties and copy each side into communications.
A surveyor who regularly acts for one side only should be particularly careful about independence when appointed jointly.
When the protocol does not have to be followed
Compliance may not be appropriate where there is a serious risk to a person's health or welfare, or where a statutory time limit applies. The protocol is also clear that it gives a landlord no reason or excuse to delay performing any legal duty [1]. Repairs should not wait for the paperwork.
What Kingston landlords should do now
- Diarise every letter of claim on the day it arrives. The 20 working days run from receipt.
- Decide quickly on the expert. Check the proposed surveyor's qualifications, experience and any pattern of acting only for claimants. Object in writing, with reasons, if there is a genuine concern.
- Read the tenant's letter of instruction. If it is one-sided, send separate instructions.
- Inspect and repair in parallel. Under Awaab's Law, social landlords have their own statutory clocks running at the same time.
- Keep records. Repair logs, inspection notes and communications with the tenant will all be asked for.
What tenants and their advisers should do
- Choose an expert who can act as a credible single joint expert: qualified, independent and willing to be instructed by both sides.
- Use the specimen letter of instruction as a base and keep the questions neutral.
- Give access promptly for the inspection, and keep dated photographs and a diary of the conditions.
- Consider alternative dispute resolution. The revised protocol expects it, and a court may ask why it was refused.
Conclusion
From 30 November 2026, housing conditions claims start from a presumption that one surveyor, instructed by both sides, will inspect within weeks and report within days. The landlord's main protection is to respond inside 20 working days. The tenant's is to nominate an expert whose independence is beyond argument. For both, the quality of the report will largely decide whether the dispute settles early or goes to court.
Landlords and tenants in Kingston, Surbiton, New Malden and nearby should check their procedures and template letters against the new text now, and identify a suitably qualified surveyor before the first deadline starts to run.
References
- Pre-Action Protocol for Housing Conditions Claims (England), approved 30 October 2026, in force 30 November 2026, Ministry of Justice. justice.gov.uk.
- Civil Procedure Rules, rules and practice directions updates, Ministry of Justice. justice.gov.uk.